Extension of Time Claim Assessment in Malaysian Construction Industry: Views from professionals

Authors

  • Norazian Mohamad Yusuwan Centre of Studies Quantity Surveying, Faculty of Architecture Planning and Surveying, Universiti Teknologi MARA, 40450, Shah Alam, Selangor, Malaysia
  • Hamimah Adnan Centre of Studies Quantity Surveying, Faculty of Architecture Planning and Surveying, Universiti Teknologi MARA, 40450, Shah Alam, Selangor, Malaysia

DOI:

https://doi.org/10.21834/aje-bs.v3i10.310

Keywords:

Construction Industry, Delay, Extension of Time Claim, Record Keeping

Abstract

This paper aims to investigate the current practice of extension of time claim assessment by contract administrators and identify difficulties faced by them during the assessment process. Findings from the questionnaire survey revealed that poor factual evidence and flaws in claim presentation are the principal factors leading to delays in the assessment process. The findings imply that efficient contract administration and well-organised record-keeping will lead not only to successful project management but also will increase the chances of a successful contractual claim. These findings are expected to offer a significant contribution to industry players, researchers and also academics, thus helping to identify areas for further improvement.

References

Akintoye, Akintola. (2000). Analysis of Factors Influencing Project Cost Estimating Practice. Construction Management and Economics, 18(1), 77-89. DOI: https://doi.org/10.1080/014461900370979

Birkby, Gillian, Ponte, Albert, & Alderson, Frances. (2008). Good Practice Guide: Extension of Time. London, United Kingdom: RIBA Publishing.

Braimah, Nuhu. (2008). An investigation into the use of construction delay and disruption analysis methodologies. (Degree of Doctor Phylosophy), University of Wolverhampton.

Carmichael, Stuart, & Murray, Maria. (2006). Record keeping for contemporaneous delay analysis: a model for effective event management. Construction Management and Economics, 24, 1007–1018. DOI: https://doi.org/10.1080/01446190500521207

Enshassi, Adnan, Mohamed, Sherif, & El-Ghandour, Said. (2009). Problems Associated with the Process of Claim Management in Palestine: Contractor's Perspective. Engineering Construction and Architectural Management, 16(1), 61-72. DOI: https://doi.org/10.1108/09699980910927895

Gibson, Roger. (2008). Construction Delays Extension of Time and Prolongation Claims: Taylor & Francis.

Hassanein, AMR A.G., & Nemr, Waleed El. (2007). Management of Change Order Claims in the Egyption

Construction Sector. Journal of Financial Management of Property and Construction, 12(1), 45-60.

Kumaraswamy, M.M., & Yogeswaran, K. (2003). Substantiation and Assessment of Claims for Extensions of Time. International Journal of Project Management, 21(1), 27-38. DOI: https://doi.org/10.1016/S0263-7863(01)00052-7

Oyegoke, Adekunle Sabitu. (2006). Building competence to manage contractual claims in international construction environment: The case of Finnish contractors. Engineering Construction and Architectural Management, 13(1), 96-113. DOI: https://doi.org/10.1108/09699980610646520

Ren, Z., Anumba, G.J., & Ugwu, O.O. (2001). Construction Claim Management: Towards an Agent-Based Approach. Engineering Construction and Architectural Management, 8(3), 185-197. DOI: https://doi.org/10.1108/eb021181

Sekaran, U., & Bougie, R. (2010). Research Methods for Business: A Skill Building Approach: John Wiley & Sons.

Yoke-Lian, Lew, Hassim, S, Muniandy, R, & Mee-Ling, Tan. (2012). The Assessment of Applications for Extension of Time Claims in Malaysian Construction Industry. DOI: https://doi.org/10.7763/IJET.2012.V4.407

Downloads

Published

2018-08-24

How to Cite

[1]
Mohamad Yusuwan, N. and Adnan, H. 2018. Extension of Time Claim Assessment in Malaysian Construction Industry: Views from professionals. Asian Journal of Environment-Behaviour Studies. 3, 10 (Aug. 2018), 28–35. DOI:https://doi.org/10.21834/aje-bs.v3i10.310.